PERFORMANCE OF COLUMN-TO-COLUMN
MECHANICAL CONNECTION IN PRECAST
CONCRETE BUILDING UNDER SEISMIC
LOADING
Ahmed D. Abdulateef*
College of Engineering, University of Samarra, Samarra 34010, Iraq.
ahmed.d.abd@uosamarra.edu.iq
Ammar A. Abdul Rahman
College of Engineering, Ashur University College, Baghdad10011, Iraq.
Reception: 17/10/2022 Acceptance: 24/12/2022 Publication: 13/01/2023
Suggested citation:
A., Ahmed D. and A. R., Ammar A. (2023). Performance of column-to-column
mechanical connection in precast concrete building under seismic
loading. 3C TIC. Cuadernos de desarrollo aplicados a las TIC, 12(1), 46-63.
https://doi.org/10.17993/3ctic.2023.121.46-63
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
46
ABSTRACT
Precast columns in precast concrete structures with floor heights require connections
that need confident, reliable, and cost-effective design and implementation methods
that can speed up both processes. At the same time, still ensure adequate strength,
stiffness, and ductility to the column behavior. Columns specifically have the main role
in structures for transmitting vertical and horizontal loads due to seismic effects to the
base to fulfill life safety requirements, but the existence of a connection in the column
cannot ensure the required. This work aims to study the performance and efficiency of
mechanical bolted column connections under the action of seismic loading. In this
regard, a column connection used in the precast structure of the new Karbala
Provincial Council (KPC) under seismic loading is used as the case study. This
building was analyzed and then designed employing special mechanical bolted
connections produced by Peikko’s products (Column-shoe & Anchor bolts). The
analysis gave the exact forces at the connection location and the design using
Peikko’s column connection performed well under all loading cases including the
seismic case. The analysis and design lead to smaller column section selection since
it takes into account the interaction of applied loads using special equations.
KEYWORDS
Column Shoe, Column to column connection, Seismic design, bolted connection,
Anchor bolts
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
47
PAPER INDEX
ABSTRACT
KEYWORDS
1. INTRODUCTION
2. DISCERPTION OF THE CONNECTION
3. COMPONENTS OF THE BOLTED CONNECTION (PBC)
3.1. Column Shoes
3.2. Anchor Bolts
4. MODELING
4.1. Modeling of the Columns
4.2. Selecting Column Connections Using Peikko Designer
5. RESULTS AND DISCUSSION
5.1. Run Analysis and Get the Results in ETABS
6. DESIGN RESULTS FROM PEIKKO DESIGNER
6.1. Corner Column (40x40 cm)
6.2. Edge Column (60x60 cm)
6.3. Corner Column (70x70 cm)
6.4. Comparison with Manual Selection:
7. CONCLUSIONS
REFERENCES
CONFLICT OF INTEREST
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
48
1. INTRODUCTION
In seismic-resistance structures with precast concrete (PC) members, the major
challenge is to find, reliable economical, applicable, and structurally accepted
methods to connect the precast elements in a way so that when subjected to cyclic
seismic loads, these connections can provide not only sufficient strength and stiffness
but also allow sufficient inelastic deformation capacity and stable hysteresis response
of the structure [1]. In framed PC structures columns particularly play a fundamental
role in transferring vertical and horizontal loads, to meet the requirement of life safety
under seismic loads. Attention should be paid to the connections between precast
columns to ensure the integrity of the building, load transfer, and the behavior under
different load combinations [2].
The ultimate strength at the joint of precast concrete
structures depends on the behavior of the material of joints between segments [3].
The connections between prefabricated elements are typically considered to be the
weakest and most critical parts Additionally, in seismic areas, the connections should
ensure that the behavior of precast connections is equal to or even better than that of
cast-in-place parts [4]. Peikko bolted column connections are considered an excellent
solution for such purposes [5]. But was not verified clearly for earthquakes. A Study on
an actual building (Karbala Provincial Council) made of precast concrete elements
(columns, beams, and hollow core slabs) that are connected by mechanical joints
(Column-shoe & Anchor bolts) will be conducted to check the adequacy and
performance of these connections in sustaining the imposed loads on the building due
to the seismic occurrence. Due to the different types of connections used in the
building, a focus will be made here in this work on the column-to-column connections
because very limited research work was published on the such connection under
seismic effects. There are limited references that deal with the characterization of
column-column connections of PC structures [6]. Also, there was limited access to
studies that examined column shoe connections due to the privacy of the product's
ownership. However, from the experimental data provided and the conclusions
gained, it is obvious that this connection system can be used in connecting the parts
of the column [7] but needs to check their performance under seismic action. Peikko
initiated an extensive experimental research program in 2008 in collaboration with the
Politecnico di Milano (Technical University of Milan) to study the performance of
Peikko's bolted column-to-foundation connections made with the HPKM column and
HPM anchor bolts. The aim was to produce and develop a prefabricated connection
that replaces the monolithic connections with the same performance in terms of
ductility, energy dissipation capacity, and stiffness [8]. The cyclic loading performance
of the Peikko bolted connection for seismic conditions needs to be verified by
extensive experimental investigations on full-scale concrete samples of precast and
cast-in-place columns. Meanwhile, numerical verification needs to be concluded to
check the adequacy of these bolted connections. The performance of the entire
connection and its components under monotonic loadings were verified by
experimental testing. The initial test with concrete column connections showed that
rectangular cross-sections with at least four-column shoes behave rigidly or at least
as stiff as in-situ concrete columns with continuous reinforcement under static loading
[10]. The tests confirmed that the bolted connection with grout between the precast
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
49
elements behaves in the same way as the corresponding monolithic reinforced
concrete column [11].
2. DISCERPTION OF THE CONNECTION
A typical mechanical bolted column connection consists of column shoes and
anchor bolts. The column shoe is placed in the formwork in the precast plant during
the production of the column at the bottom end of the upper column and the anchor
bolts are cast in the upper end of the lower column in case of column-column
connection or cast in-site into the foundation in case of column-foundation connection
as shown in Figure (1). The protruding threaded portion of the bolt allows the column
shoe base plate to be tightened with a pair of washers and nuts. The tightening of the
connection under seismic loading is also ensured by high-strength lock washers. The
connection is completed by filling the joint between the columns or the column and the
foundation with high-durability, non-shrinking mortar. Once the mortar has reached its
design strength, the connection behaves as a reinforced concrete connection. The
shear force transmission is done by anchor bolts with lock washers and mechanical
locking between mortar and concrete. The design compressive strength of the grout
should be at least one class higher than the highest concrete grade of the jointed
elements, to avoid the brittle fracture of the concrete at the joint. [8]. Assembling the
column shoes on the column requires steel boxes called Recess boxes containing two
types (C and M) as shown in figure (2), their cost is low and they can be used multiple
times to prevent concrete from filling the shoe hole during casting of the column.
Figure 1. Typical bolted column connection [12]
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
50
Figure 2. (C and M) types of Recess boxes [12]
3. COMPONENTS OF THE BOLTED CONNECTION
(PBC)
3.1. COLUMN SHOES
Column shoes are products used to create moment-bearing connections between
precast concrete elements, such as columns, foundations, and walls. The bolted
column shoe connection is at least as stiff as a cast-in-place column connection with
continuous reinforcement. The loads on the connection are first distributed to the
individual column bases. The shear strength of a column shoe is equal to the shear
strength of the corresponding anchor bolts [12]. The strength of the column shoe
corresponds to the strength of the corresponding anchor bolts. Four or more column
shoes can be used in one column cross-section [7]. figure (3) shows Peikko’s column
shoes that are used here.
Figure 3. Peikko bolted connection (PBC) for column (a) HPKM column shoe [13], (b) BOLDA
column shoe [14]
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
51
3.2. ANCHOR BOLTS
Anchor bolts can provide a solution for most precast connections (e.g., column -
foundation, column - column, wall - foundation, wall - wall) as well as fastening of steel
columns or even machine fastenings. It’s available as L- a type use in shallow
structures (e.g., foundations, slabs, beams) due to their relatively short anchor length
and P-type for structures with sufficient depth (e.g., pedestals, and columns). if the
tensile or shear strength of the anchor bolt steel is insufficient, additional
reinforcement may be used to withstand the forces on the anchor bolt and if the
concrete cone resistance is exceeded, supplementary reinforcement for the tension
load should be provided. reinforcement arrangements can be calculated using the
Peikko Designer software following EN 1992-4. With Peikko Designer software it is
possible to select the appropriate type and number of anchor bolts to be used in a
connection and to check the strength of the connection [13]. During the assembly
phase, the forces acting on the anchor bolts are mainly caused by the weight of the
column itself and the bending moment and shear force due to the wind load. Since the
connection is not grouted, all forces from the column shoe are only absorbed by the
anchor bolts. therefore, it must be designed for buckling and bending [12]. The anchor
bolts used in column connections are shown in the figure. (4).
Figure 4. Anchor bolts. A) HPM Rebar Anchor Bolts Type L & type P [15]. B) High Strength
Steel Anchor Bolts Type (L & P) [16]
4. MODELING
4.1. MODELING OF THE COLUMNS
Simulation models have the characteristic of being a technique for solving practical
problems [17]. The whole structure of the building was divided into seven structures
(Blocks) with expansion joints each part was modeled using CSI ETABS Software to
analyze the effect of all external forces including seismic forces for the Karbala area
according to the Iraqi Seismic Code. These forces were applied to the building and
the magnitude of all internal forces acting on the columns at different stations through
their total height was obtained. ETABS can give the magnitude of internal forces at
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
52
(0%, 25%,50%,75%, and 100%) of the column’s height. This feature could be very
useful in the design of the connection since it can help in identifying the magnitude of
internal forces corresponding to desired connection location. There are three different
column cross-sections in each of the seven blocks (40x40, 60x60, and 70x70 cm)
respectively distributed at different positions on the plan (corner, edge, interior). In this
work, Block number 7 figure (5) is considered only for these calculations. The seismic
details defined in the ETABS model are shown in figure 6
Figure 5. ETABS model of part 7
Figure 6. The seismic details defined in the ETABS model
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
53
4.2. SELECTING COLUMN CONNECTIONS USING PEIKKO
DESIGNER
For column-to-column connection, HPKM & BOLDA column shoes with HPM &
PPM anchor bolts were respectively chosen. The selection of the suitable size of
column shoes and anchor bolts to be used for connecting the precast segments was
first done manually based on the technical manual provided. The selection of the
connection components was verified using Peikko designer software. The software
contains a predefined module for different types of column shoes and their
corresponding anchor bolts. In the software, there is an implemented design code
selection. By selecting the required valid design code, it is possible to check the
resistances of each column connection.
5. RESULTS AND DISCUSSION
5.1. RUN ANALYSIS AND GET THE RESULTS IN ETABS
After completing the modeling in ETABS, the analysis process will start to get the
magnitude of all internal forces acting on the columns at the selected sections of the
columns. After that, the analysis results were filtered, sorted, and rearranged to be
used in the next step (Selection of Suitable connection items by Peikko designer). The
analysis results used in the selection of the connection components (column shoes +
anchor bolts) were selected based on the location of the column i.e., (corner 40x40,
edge 40x40, 40x40 interior, 60x60 corner …etc.). For simplicity and to avoid getting a
huge number of designed connections for each column cross-section at each location
and each story only the greatest values of internal forces on each column cross-
section concerning its location due to the application of all types of loads including
earthquakes were used to design the connections as shown in figures ((7) - (10)) and
Table (1). The manufacturer can use any length of each segment that his factory can
produce. The columns were made of three parts only taking into account that each
column consists of three individual precast segments to
be connected to cover the
total height of the building.
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
54
Figure 7. The Column that was subjected to the higher magnitude of internal forces &
moments.
Figure 8. Corner Column 40x40 cm that was subjected to the highest magnitude of internal
moments. (a) X-direction, (b) Y-direction.
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
55
Figure 9. Edge Column 60x60 cm that was subjected to the highest magnitude of internal
moments. (a) X-direction, (b) Y-direction.
Figure 10. Interior Column 70x70 cm that was subjected to the highest magnitude of internal
moments (a) X-direction, (b) Y-direction.
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
56
Table1. Analysis results of the building (Block-7) columns under the effect of all types of
loadings including earthquake from ETABS software after filtering, sorting, and rearranging
The positive (+ve) values of axial forces (P) refer to tension forces due to seismic
effect. However, their values were relatively small due to the weight of the entire
building which tends to resist the tension forces. While the negative (-ve) values
referred to compression forces due to both gravity load and seismic action. The shear
forces sign referred to the direction of forces in the XY plane. While the Moments sign
referred to whether the rotation will induce tension or compression forces on the
column. The reason why there were (+ve) and (-ve) values were seismic action.
6. DESIGN RESULTS FROM PEIKKO DESIGNER
To Design the column connection (Choosing the right number and size of column
shoes and anchor bolts to resist the Seismic loads) the analysis results of Table (1)
were used in Peikko designer to check the chosen connection. Design results for one
cross-section of each location (corner 40x40, edge 60x60, and interior 70x70) will be
presented here. Peikko designer can provide a detailed report for the design process.
When no more HPKM Column Shoes can fit in the cross-section to reach the required
resistance BOLDA column shoes should be used instead.
6.1. CORNER COLUMN (40X40 CM)
Use 4 (HPKM column shoes - HPM anchor bolts) size 30 with 2 (HPKM column
shoes - HPM anchor bolts) size 20 at the middle of the column lower face in the x-
direction to satisfy the capacity requirements rather than using 6 (HPKM column
shoes - HPM anchor bolts) size 30 for economic reasons and to provide more spacing
for concrete as shown in figure (11). The design report indicates that the resistance of
the connection was within the safe limits of the selected code provisions. And no
failure in both the concrete or steel items (column shoes and anchor bolts). The green
dot in the resistance diagram between the moments and the axial forces represents
Position
Column
sec.
P (kN) Vx (kN) Vy (kN) Mx (kN-m) My (kN-m)
C40x40 (cm)
corner (40x40) 9.8163 22.2389 49.9546 120.3723 64.2164
corner (40x40) -220.233 -19.372 -35.301 -136.1899 -56.6916
C60x60 (cm)
edge (60x60) 153.0051 85.4763 149.125 304.5703 193.6522
edge (60x60) -2532.4829 -99.1011 -143.181 -358.2493 -246.6811
C70x70 (cm)
interior (70x70) 138.4 76.3252 124.0431 333.7802 468.9884
interior (70x70) -3607.5895 -242.6262 -126.1854 -369.5490 -569.6058
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
57
the applied load of the column while the dashed line refers to the connection capacity.
As shown in figure (12).
Figure 11. HPKM column shoe & HPM anchor bolts 1st configuration (4 size30 +2 size20)
Figure 12. Resistance diagram of the connection, (a)- Resistance in the X direction, (b)-
Resistance in the Y direction
6.2. EDGE COLUMN (60X60 CM)
Use 4 (BOLDA column shoe - PPM anchor bolts) size 39 as shown in figure (13).
The design report indicates that the resistance of the connection was within the safe
limits of the selected code provisions. And no failure in both the concrete or steel
items (column shoes and anchor bolts). The green dot in the resistance diagram
between the moments and the axial forces represents the applied load of the column
while the dashed line refers to the connection capacity. As shown in figure (14).
Figure 13. BOLDA column shoe & PPM anchor configuration (4 size39)
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
58
Figure 14. Resistance diagram of the connection. (a)- Resistance in the X direction, (b)-
Resistance in the Y direction
6.3. CORNER COLUMN (70X70 CM)
Use 4 (PPM anchor bolts & BOLDA column shoe) size 45 as shown in figure (15).
The design report indicates that the resistance of the connection was within the safe
limits of the selected code provisions. And no failure in both the concrete or steel
items (column shoes and anchor bolts). The green dot in the resistance diagram
between the moments and the axial forces represents the applied load of the column
while the dashed line refers to the connection capacity. As shown in figure (16).
Figure 15. BOLDA column shoe & PPM anchor bolts (4 size45)
Figure 16. Resistance diagram of 4 - size - 45 configuration. (a)- Resistance in the X
direction, (b)- Resistance in the Y direction
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
59
Or we can use 6 (PPM anchor bolts & BOLDA column shoes) size 39 as shown in
figure (17). The design report indicates that the resistance of the connection was
within the safe limits of the selected code provisions. And no failure in both the
concrete or steel items (column shoes and anchor bolts). The green dot in the
resistance diagram between the moments and the axial forces represents the applied
load of the column while the dashed line refers to the connection capacity. As shown
in figure (18). Whichever is more economical.
Figure 17. BOLDA column shoe & PPM anchor bolts 2nd configuration (6 size39)
Figure 18. Resistance diagram of the 6 – size 39 configuration. (a)- Resistance in the X
direction, (b)- Resistance in the Y direction
6.4. COMPARISON WITH MANUAL SELECTION:
The results from the Peikko designer for precast column-to-column connection
were compared with those from a manual selection as follows. The manual selection
was done by the capacity tables that the technical manuals of these items contain.
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
60
Table 2. Comparison with Manual Selection
7. CONCLUSIONS
The column shoe connection system seems to have the same advantages as other
connection types, but also very fewer disadvantages. The main drawback is that may
be considered a relatively expensive solution, especially in certain markets. However,
when choosing this solution, one should keep in mind that it saves materials since it
ensures a much faster installation process than other solutions and a simple design
process. These types of bolted connections (HPKM column shoes with HPM anchor
bolts and BOLDS column shoes with PPM anchor bolts) do not require bracing due to
the instantaneous mechanical fixing during assembly and a small amount of grouting
is required for both types. A great advantage of Column shoes is considered a
universal solution for connecting columns. Due to the existence of design tools, it is an
easy, fast, and guaranteed way to create a design of this connection. This can lead to
shorter duration and less cost in the project design work stage. In addition, it has good
performance against seismic or dynamic loads, which gives additional security to the
whole structure and was considered a shortage in all precast structures (not fulfilling
the seismic requirements). It is necessary to choose a sufficiently strong column shoe
and the appropriate anchor bolt in addition to a correct installation process to
guarantee the performance of this type of connection system. From all of the above,
the following can be concluded:
1.
With the grouting mortar the shoe connection behavior is very similar to the
behavior of the in-situ concrete column under seismic action.
2.
The selection of column shoes and anchor bolts can be easily done with design
tools such as Peikko Designer. However, it is very important to pay more attention
when seismic, dynamic, or fatigue loads are considered.
3. Most of the stresses are concentrated on the shoe rods. Therefore, when using the
column shoe system. this could provide a more economical use for the main
reinforcement than a cast-in-place case
4.
The column connection items chosen ensured that the principle of the strong
column-weak beam is still valid since they provide a strong column connection.
No
.
Column cross-section Manual-selection Peikko-selection
1 Corner Column 40x40 4 (HPM anchor bolts & HPKM
column shoes) size 39
4 (HPM anchor bolts &
HPKM column shoes) size
30 with 2 (HPM anchor
bolts & HPKM column
shoes) size 20 at the
2 Edge Column 60x60
4 (PPM anchor bolts & BOLDA
column shoe) size 45
4 (PPM anchor bolts &
BOLDA column shoe) size
3 Corner Column 70x70 4 (PPM anchor bolts & BOLDA
column shoe) size 52
4 (PPM anchor bolts &
BOLDA column shoe) size
45 or 6 (PPM anchor bolts
& BOLDA column shoe)
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
61
5. The column connection items chosen can be used in demountable frames because
they are removable.
6.
More than one size of the same type of column shoe can be used at once in the
same cross-section.
REFERENCES
(1) Park, R. (1995). A perspective on the seismic design of precast concrete
structures in New Zealand. PCI journal, 40(3).
(2) Rodrigues, H., Arede, A., Varum, H., & Costa, A. (2012). Behavior of RC
building columns under cyclic loading: Experimental study. Journal of
Earthquake and Tsunami, 6(04), 1250026.
(3) Ardiyati, P., Handika, N., & Purnomo, H. (2021). Non-linear modelling of Ferro
casting ductile shear key of L-Shaped concrete blocks with epoxy joint
using Midas FEA. 3c Tecnología: glosas de innovación aplicadas a la pyme,
10(3), 101-117. https://doi.org/10.17993/3ctecno/2021.v10n3e39.101-117
(4) Yu, J., Zhang, W., Tang, Z., Guo, X., & Pospíšil, S. (2020). Seismic behavior of
precast concrete beam-column joints with steel strand inserts under cyclic
loading. Engineering Structures, 216, 110766.
(5) Camnasio E., Özer C. (2021). Bolted Connections for Precast Structures in
Seismic Areas Peikko Solutions and Design Examples. Peikko White Paper,
1-12.
(6) Rave-Arango, J. F., Blandón, C. A., Restrepo, J. I., & Carmona, F. (2018).
Seismic performance of precast concrete column-to-column lap-splice
connections. Engineering structures, 172, 687-699.
(7) Abezgaus, S. (2020). Investigation of column shoes (Doctoral dissertation,
Vilniaus Gedimino technikos universitetas).
(8) Camnasio E. (2017). Bolted Column Connection for Seismic Applications.
Peikko White Paper, 1-4.
(9) Paananen T. (2017). Peikko is the first company to introduce seismic-proof
precast bolted column connections. https://www.peikko.com/news/peikko-is-
the-first-company-to-introduce-seismic-proof-precast-bolted-column-
connections-2
(10) Peikko Group Technical Manual. (2019). Bolted Column Connection (For
Seismic Applications) Seismic-Proof Application of Bolted Connections.
(11) Kinnunen, J. (2017). ETA tests and design of HPKM Column Shoe
Connections. Procedia Engineering, 172, 521-528.
(12) Peikko Group Technical Manual. (2022). HPM Rebar Anchor Bolt Easy and
fast bolted connections European Technical Approval ETA-02/0006.
(13) Peikko Group Technical Manual. (2017). HPKM Column Shoe Reliable Bolted
Column Connections Designed according to ACI 318M-11.
(14) Peikko Group Technical Manual. (2021). BOLDA Column Shoe Strong and
Optimized Bolted Column Connections European Technical Assessment
ETA-20/0529 Approved.
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
62
(15) Peikko Group Technical Manual. (2018). PEC Column Shoe Heavy-duty
Bolted Column Connections.
(16) Peikko Group Technical Manual. (2021). PPM High-Strength Anchor Bolt
Heavy-duty bolted connections.
(17) Kaseng, F., Condori, L. J. C., & Rodriguez, C. R. (2020). Mix design with
response surface methodology to optimize the flexural strength of
concrete. 3c Tecnología: glosas de innovación aplicadas a la pyme, 9(3), 47-57.
https://doi.org/10.17993/3ctecno/2020.v9n3e35.47-57
CONFLICT OF INTEREST
The authors declare that the research was conducted in the absence of any
commercial or financial relationships that could be construed as a potential conflict of
interest.
https://doi.org/10.17993/3ctic.2023.121.46-63
3C TIC. Cuadernos de desarrollo aplicados a las TIC. ISSN: 2254-6529
Ed.42 | Iss.12 | N.1 January - March 2023
63